In Japan, a grid-scale battery energy storage project can be considered Ready to Build (RTB) once all required development tasks are completed and supporting documentation is obtained.
The key requirements are as follows:
1. Grid Connection Study Response
Official document issued by the utility (e.g., TEPCO, KEPCO) confirming technical conditions, construction schedule, interconnection cost, and approved capacity.
This is the most critical document confirming grid feasibility.
2. Grid Connection Study Application
Formal application submitted to initiate the interconnection review process.
Includes project capacity, location, equipment specifications, and land rights documentation.
3. Land Registry Certificate
Legal proof of land ownership, zoning, encumbrances, and area.
Confirms land suitability for energy storage development.
4. Site Master Plan
Detailed layout showing boundaries, terrain, structures, and surrounding infrastructure.
Used for EPC design, grid routing, and construction planning.
5. Hazard Risk Map
Government-issued disaster risk data covering earthquakes, floods, and landslides.
Required for safety assessment and environmental compliance.
6. Archaeological Survey Clearance
Investigation confirming whether underground cultural artifacts exist.
Required under Japan’s Cultural Properties Protection Law.
7. Regulatory Compliance Status Report
Comprehensive report summarizing progress of all legal approvals including environmental permits, grid procedures, and safety approvals.
Key document for investor due diligence.
8. Interconnection Deposit Receipt (5%)
Proof of payment of the utility interconnection deposit.
Secures grid capacity and confirms advancement to formal review stage.
9. Site Photographs
Visual documentation of site conditions, infrastructure, and surroundings.
Used for verification and engineering planning.
When all of the above are completed, the project is considered fully developed from a permitting and interconnection standpoint and qualifies as Ready to Build (RTB).